News
Regulatory Links
Proposal Request
Community Involvement
Site Map
|
 |
The NYSDEC
recently revised dam safety regulations in an effort to protect
the public as well as clearly define dam owner responsibilities.
The revised dam safety regulations apply to dams that are 15
feet or higher or have a capacity of greater than three million
gallons.
The revised dam regulations require dam
owners to complete the following:
-
Inspection & Maintenance Plan
– Establish procedures to ensure dam safety and fitness. Must
be completed by August 19,
2010.
-
Emergency
Action Plan (Intermediate and High) – Comprehensive
summary of procedures to undertake in the event of a potential
life threatening event at or near the dam (i.e. dam breach,
flooding, unnatural disaster). Must be completed by August
19, 2010 for High Hazard Dams and August 19, 2011 for
Intermediate Hazard Dams.
-
Annual
Certifications (Intermediate and High) – A mandatory
filing to DEC verifying information pertaining to the dam.
-
Safety
Inspections (Intermediate and High) – Completed by an
engineer to assess the fitness of the dam.
HRP Associates, Inc.’s dam safety
professionals have experience implementing these new dam safety
regulations through their work with various state agencies.
If you require additional information,
or would like to schedule a site visit to discuss these revised
regulations, please contact
Jeffrey Mannion
or
Thomas Seguljic, P.E.
at 518-877-7101.
|
|